STANDARD OPERATING PROCEDURES
SOP-CT-00 CONTRACT
Ref1>.No Contents
SOP-CT-01 Taking –off of Quantities
SOP-CT-8>02 Calling and Awarding of Sub-Contracts
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO :
SOP-CT- 01
( ...
新加坡金字塔公司
模式英文版(2)[全文]
STANDARD OPERATING PROCEDURES
SOP-CT-00 CONTRACT
Ref1>.No Contents
SOP-CT-01 Taking –off of Quantities
SOP-CT-8>02 Calling and Awarding of Sub-Contracts
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO :
SOP-CT- 01
( Page 1/1 )
WORK TITLE :
Taking –OFF of Quantity
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA : 18.10.97
WORKMANSHIP STANDARD : ACCEPTANCE /REJECTION CRITERIA
NA
REFERENCE STANDARDS/ CODES & QUALITY PLAN :
NA
FACILITIES /INSPECTION INSTRUMENT :
NA
ENVIRNMENT CONTROLS :
NA
NECESSARY RECORDS :
1.Cob\ntractual /tender documents
2. Construction drawings
3. Taking –off formats ( Appendix 1 ( a) and 1 ( b ) )
FREQUENCY :
During planning stage and before commencement of project
SPECIAL REQUIREMENTS :
SAFETY & HEALTH REQUIREMENTS
Safety Orientation Course for workers
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPONSIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Quantity Surveyor
1. Senior Quantity Surveyor /Quantity Surveyor is to extract quantities from contractual /tender documents for basic materials such as reinforcement, ready –mixed concrete, brick , etc
2..Take off quantities from construction drawings using the formats attached ( Appendix 1 (a) and 1 (b ) or similar formats
3.Project title , month/date of taking off done must be filled up in Appendix 1 (a ) and 1 ( b)
4. Total up the quantities by page
5. Summaries the quantities by using the pink formats attached ( Appendix 2 (a) and 2 (b ) or similar formats
Verify against contractual /tender documents
Construction drawings and see also Appendix 1 (a) and 1 (b) attached
NA
NA
See Appendix 2 (a) and 2 (b) attached
NA
NA
NA
NA
NA
P
P
P
P
P
File : CT -01 DISK: SOP
A : APPROVE F : CONFIRM P : PERFORM
C: CHECK
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO :
SOP-CT- 02
( Page 1/2 )
WORK TITLE :
Calling and Awarding of Sub- Contracts
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA : 18.10.97
WORKMANSHIP STANDARD : ACCEPTANCE /REJECTION CRITERIA
NA
REFERENCE STANDARDS/ CODES & QUALITY PLAN :
NA
FACILITIES /INSPECTION INSTRUMENT :
NA
ENVIRNMENT CONTROLS :
NA
NECESSARY RECORDS :
1. Contractual /tender documents 5. Survey of Sub-contractor
2. Quotations 6.
Consolidated List of Letter of Award (Appendix 3 )
3. Approved Sub-contractor List 7. Check List for approved
sub- contractor
4. letter of Award
FREQUENCY :
During planning stage and before commencement of project
SPECIAL REQUIREMENTS :
SAFETY & HEALTH REQUIREMENTS
NA
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPONSIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Quantity Surveyor
1. Senior quantity Surveyor/Quantity Surveyor to go through contractual /tender documents and
itemize the trades to be sub- contracted
2. priorities shall be given to the following trades :
a) land Surveyor
b) soil treatment
c) earthwork
d) piling
e) water proofing to sub –stations
f) material testing laboratory
g) carpenter
h) steelbender
i) concretor
j) scaffolder
Contractual /tender documents
NA
NA
NA
P
P
File : CT--02 DISK: SOP
A : APPROVE F : CONFIRM P : PERFORM
C: CHECK
PARK HYATT SAIGON HOTEL PROJECT
STANDARD OPERATION PROCEDURE NO :
SOP-CT- 02
( Page 2/2 )
WORK TITLE :
Calling and Awarding of Sub- contractors
APPROVED BY :
Head, Control Dept
CHECKED BY :
PROJECT MANAGER
REVISION : A
EFFECTIVE DATA : 18.10.97
WORK PROCEDURE
CHECKING METHOD
REMEDIAL MEASURE
RESPONSIBILITY
Project Manager
Engineer
Foreman
Assistant Foreman
Trade Worker
Checker
Subcon
Quantity Surveyor
3..If sub-contractor is not in the Approved sub-contractor list , the surveyor of sub- contractor is
to be filled
4. Approve the award of contract and dispatch the letter of Award
NA
NA
NA
NA
A
P
P
File : CT -02 DISK: SOP A : APPROVE F : CONFIRM P : PERFORM C: CHECK
本文档为【新加坡金字塔公司项目管理模式英文版(2)[全文]】,请使用软件OFFICE或WPS软件打开。作品中的文字与图均可以修改和编辑,
图片更改请在作品中右键图片并更换,文字修改请直接点击文字进行修改,也可以新增和删除文档中的内容。
[版权声明] 本站所有资料为用户分享产生,若发现您的权利被侵害,请联系客服邮件isharekefu@iask.cn,我们尽快处理。
本作品所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用。
网站提供的党政主题相关内容(国旗、国徽、党徽..)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。