DEMANDING HDD INSTALLATION OF FUSIBLE 24-INCH PVC PIPE SETS
NEW RECORD
Jerry Shae1, Jeremy King2, and Richard (Bo) Botteicher3, PE, M.ASCE
1 Project Engineer, Bartlett and West Inc; 3456 E. Century Avenue, Bismarck, ND; PH
(701) 258-1110; email: jerry.shae@bartwest.com
2 President, King Contracting Inc.; 7141 Amanda Rd., Lincoln, NE; PH (402) 476-
3030; email: jeremyking@kinghdd.com
3 Senior Product Engineer, Underground Solutions Inc.; 1869 S Eudora St., Denver,
CO 80222; PH (303) 521-2618; email: bbotteicher@undergroundsolutions.com
ABSTRACT
Horizontal directional drilling (HDD) has played a major role in allowing
construction of a raw water delivery system project for the Standing Rock Sioux
Tribe in South and North Dakota. A record setting 1,463 m (4,800 LF) bore under a
dam-retained section of the Grand River, Oahe Lake, of 600 mm (24-inch) Fusible C-
905® pipe has defined an early success on the 110 million dollar project. King
Contracting, Inc. (King) completed the bore which represents the longest bore ever
done using 600 mm (24-inch) Fusible PVC™ pipe (FPVCP) to date. This crossing
represents a little less than 1.5 km of the ~100 km (62 miles) raw and treated water
transmission pipeline delivery system, which when completed, will provide water to
the Standing Rock Reservation.
INTRODUCTION AND PROJECT BACKGROUND
The Standing Rock Reservation is home to the Standing Rock Sioux Tribe, and is
located in north central South Dakota and south central North Dakota. The
reservation itself encompasses an area of ~9310 km2 (2.3 million acres) which is
slightly smaller than the state of Connecticut. The lack of a reliable municipal water
source has plagued the reservation for several years. Recent federal funding has
helped to alleviate this problem through the development of an area wide municipal
water system, the Standing Rock Rural Water System. This particular project is part
of a “core facilities system” which will provide reliable drinking water to
approximately 75% of the reservation’s population.
The reservation wide engineering plan which was compiled by Bartlett and West, a
full service engineering firm located in Bismarck, ND, was comprised of several
elements. The core facilities project includes a caisson-style intake on the Lake Oahe
31Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
reservoir, a 19,000 m3/day (5 MGD) water treatment plant, a 19,000 m3 (5 million
gallon) primary storage reservoir and approximately ~100 km (62 miles) of large
diameter main line piping. Estimated cost of this portion of Standing Rock Rural
Water System approaches $60 million. The entire reservation system will take 10
years to complete at a total cost of approximately $130 million.
The initial stage of the Standing Rock Rural Water System included the design and
construction of a raw water intake and treatment plant. Due to physical and political
constraints, the intake and treatment plant were to be located approximately 19.3 km
(12 miles) apart. A pipeline alignment connecting these two elements required the
crossing of the Grand River with a raw water line at a point where its width
approaches 1.5 km (~1 mile). Due to environmental friendliness, ease of permitting
and relatively clean operation, horizontal directional drilling was chosen as the
construction method for this stretch. Open excavation techniques were only
preliminarily considered for this crossing.
The Grand River crossing portion of the raw water line involved design
complications related to pipe material selection as well as installation. The portion of
the raw water line which was intended to pass under the Grand River would also be
the portion where the highest static pressure would occur. In order to provide an
adequate factor of safety and the necessary restraint for large diameter pipe in this
area, three alternate materials were selected, FPVCP Fusible C905 DR 18, HDPE DR
7.3, and Cross Linked HDPE DR 9, with the ultimate selection being made by the
successful contractor. In order to minimize friction loss and ultimately meet the pipe
interior diameter requirements for the project, FPVCP of 600 mm (24-inch) nominal
diameter would be necessary and HDPE of 760 mm (30-inch) nominal diameter
would be necessary. Ultimately FPVCP was chosen as the crossing material for a
variety of reasons including the smaller outside diameter relative to inside diameter
and the availability of material.
CROSSING LAKE OAHE
An HDD project of this length and size was going to be complicated enough, but this
project had some additional aspects that made it an even greater challenge for both
the driller and the product pipes that could be used.
The alignment required that a fairly significant body of water be crossed, as it was
located on a portion of the damned up Grand River at the bottom end of an area
known as Lake Oahe. When the project was designed, the average lake level was
estimated at an elevation of 485 m (1,592 ft); this measurement being taken in the
summer of 2008. This placed the deepest point of the proposed drill under about 12
m (40 feet) of water at this level.
There was also significant topography located on either side of the crossing, with
steep banks rising out from the lake edges for another 15 to 24 m (50 to 80 feet),
depending on which side of the crossing evaluated. While this had limited effects on
32Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
the drilling rig and related equipment placement and operations, it did have a very
large effect on the fusion and stringing of the product pipe for staging the pull and
then performing the insertion operation. Figures 1 and 2 show plan and profile views
of the HDD crossing of Lake Oahe.
Figure 1. Plan view of the original crossing as designed (Bartlett and West).
Figure 2. Profile view of the original crossing as designed (Bartlett and West).
Additionally, geotechnical information for the site showed a varied cross-section of
soils that would be encountered by the drilling. This had less of an impact on the
33Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
pipe for the crossing, than it did for the actual process of boring the cavity to install
it.
Finally, the remoteness of the site further complicated the construction process. Not
only would more standard construction supplies be limited, the more specialized
HDD tooling and components would be impossible to find locally. This meant that
contingencies and extra parts and supplies particular to the operation were a must. A
significant amount of planning went into the mobilization of the drilling process to
the site (Bueno).
BEGINNING THE WORK
The initial project scope seemed fairly daunting – but the events leading up to the
actual construction provided even more challenges. A snowy winter, and then a very
rainy spring meant that when this work was to begin, the lake level that was
estimated at 12 m (40 feet) at the deepest point went to 18 m (60 feet). Not only did
the water get deeper, it also spread its horizontal reach up both banks of the crossing
site, and in doing so placed the proposed location of the drilling, pipe fusion, and
staging operation under water.
This brought about the largest change in the project, which was to switch the
direction of the insertion and drilling processes and also to lengthen the bore so that it
could be completed from the ‘tops’ of both banks, instead of as close to the water’s
edge as was originally possible. The bored crossing then went to approximately 1463
m (4,800 feet) as opposed to ~1280 m (~4,200 feet) as originally designed. It also
got relatively deeper, due to the new locations of the bore and insertion pits.
With the new direction of installation, the fusion process and pipe layout moved to
the North side of the crossing, which presented several of its own challenges. The
terrain of the north side of the crossing as well as the presence of several driveways
required some creative solutions in order to assemble the entire length of 600 mm
(24-inch) nominal diameter pipe into one single string.
DRILLING PROCESS
King Contracting, Inc (King) of Lincoln, Nebraska, won the project and was tasked
with drilling this very difficult crossing. King has performed many HDD
installations ranging in difficulty over the years and specializes in all types of
pipeline crossings including waterworks installations, like this project, and also oil
and gasoline crossings more common to industrial work (Bueno).
The weather encountered leading up to the project created challenges for the drilling
as well as the overall plan of attack for the bore as previously described. One major
complication that arose during the drilling process that was affected by the water
level increase was the ability to track the pilot bore using a guidance system.
Traditionally, a wireline system is used to track and locate the drilling head during a
34Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
pilot bore of this length and magnitude, so that the alignment can be verified against
the steering process used to guide the creation of the pilot bore. King used a wireline
system and steering company in Centerline Directional Guidance Systems
(Centerline), but they ran into trouble placing the coils required in the Lake. Divers
were used to attempt to place the coil wire on the bottom of the lake, but the extra 6
m (20 feet) of depth due to the rainy spring and strong crosswinds and currents meant
that accurate survey from the bottom of the lake was nearly impossible. Centerline
laid their wireline system as far as they could operate it effectively, and then drilled
the pilot bore ‘blind’ under the water, using only the steering corrections made to
estimate where the pilot bore was at any given time for the bulk of the crossing.
Even given these circumstances, they were able to hold the bore within 1.5 m (5 feet)
of the proposed alignment when they reached the other side of the water and were
able to locate the pilot equipment. Figure 3 shows the drilling rig and operational
setup.
Figure 3. Drilling Setup used for the reaming and pullback phases of construction,
AA625 drill rig and ancillary equipment.
A Vermeer 200x300 drill rig was used to install the pilot bore at a diameter of 250
mm (9 and 7/8 inches). This was the first indication that the soils present for the bore
were going to provide a challenge. The pilot bore took approximately 10 days to
complete, while dealing with the differing soils present and struggling to keep down-
hole tooling matched to the conditions present at any given time in the bore. Soil
conditions along the alignment varied from clay to shale to silty sand. It was difficult
35Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
for the tooling to keep most of the shale, which actually tended to be very soft, from
sticking to hole openers used.
King used the same Vermeer drill rig for the first reaming pass, but ultimately used a
larger American Augers AA625 for the second 38-inch ream and then pipe pullback.
They ultimately settled on a homemade reamer, which helped with the difficulties
associated with the soft shale as mentioned above, but then struggled to get through
the pockets of much harder shale that were also present.
The soils present were a challenge for the entire drilling process from start to finish.
Due to these complications and longer bore length, the reaming process took about
three weeks longer than expected.
FUSIBLE PVC™ FOR THE CROSSING
FPVCP was bid as an option for the crossing and was selected for the crossing by
King. The tensile properties of PVC lend themselves very well to a crossing of this
type, as long as they can be effectively utilized by the joining methodology of the
pipe. The ability to fuse PVC pipe has created this ability for long strings of pipe,
such as the one required for this project. Figure 4 shows the fusion process for
FPVCP. Additionally, the tensile capacity of the plastic allows a higher pressure class
to be attained with a thinner wall compared to other fusible thermoplastic systems.
This ultimately means a larger flow area for a given outer diameter, which results in
reduced construction costs in a smaller total bore hole size required – reducing
reaming passes, drilling fluids, and the time required to complete a crossing – all
saving construction dollars and perhaps more importantly, time on site.
Figure 4. Fusion Setup – Joining lengths of pipe for the insertion.
36Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
Underground Solutions, Inc. (UGSI) provided the 600 mm (24-inch) DR18 Fusible
C-905 pipe for the crossing and also performed the fusion services to assemble the
pipe on site. As mentioned previously, the new direction and length of the
installation required that 1463 m (4,800 feet) of pipe be strung along an existing
roadway, complete with driveways and a difficult topography. To handle the required
topography and to facilitate easier movement of the pipe string, the pipe was placed
on appropriately sized and spaced rollers as shown in Figure 5.
Figure 5. Pipe String Layout with rollers
The driveways were handled by replacing existing drainage piping with oversized,
915 mm (36-inch) CMP culverts and then stringing the pipe through those culverts
with a roller at either side. The driveway was excavated, the culvert placed at the
approximate location, FPVCP pipe was then threaded through, and the alignment of
the composite section was adjusted. Finally, the crossing was backfilled and then
plated to allow access while the rest of the staging continued. This assured the pipe
would be out of the way for the staging process and then again during installation,
while access via the driveway was maintained as shown in Figure 6. The culverts
were then left in place after the work was completed to function as a drainage
crossing.
37Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
Figure 6. Pipe String Layout with Driveway Access Crossing Shown.
PIPE INSERTION AND HDD COMPLETION
Once the borehole was completed and the alignment was set up for insertion, the pipe
was prepared for pullback and final placement. Insertion began on August 19th,
2009, at around 8am, as shown in Figure 7. The pullback process continued until
3pm when a contaminated joint was discovered at the 622 m (2,040 foot) mark of the
insertion. The pullback process was ceased at this point until the joint could be
removed and re-fused together. This process took some time, in order to get the
appropriate personnel back on site, and due to the handling required of the long string
of pipe that was still present on the surface side, waiting to be pulled in. The new
joint was completed the next day at noon, and pullback was restarted. This process
took almost another 10 hours to complete, and at 9:45 PM, August 20th, 2009, the line
was completed. A total length of 1463 m (4,800 feet) was installed.
38Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
Figure 7. Insertion pit and beginning of pullback operation
During the insertion process, a waterline was installed in the pipe that stretched the
length of the staged pipe and down into the insertion pit. This line was then used to
pump water into the PVC as it was installed, thus filling it with ballasting agent
(clean water) which reduced the buoyancy effect of the pipe on the top of the
borehole. This provides several benefits, the greatest of which is the reduction of pull
forces required that act on the drill rig and the pipe itself during the installation
process. The average pull force for the drill in total was about 160,000 lbs. Towards
the end of the installation, over the last 152 m (500 feet) or so, when pull forces are
expected to be the greatest, the required calculated force at the drill rig was recorded
at approximately 200,000 lbs. The 600 mm (24-inch) nominal Fusible C-905, DR 18
pipe has a safe allowable pull force recommendation of 305,000 lbs. This value
includes a 2.5 safety factor on the tensile capacity of the pipe and joints.
Other best practices employed in the insertion process were the use of adequately
sized and spaced rollers to support the pipe string above ground, observation of the
alignment to assure that the pipe was not over bent, or in danger of pulling off the
rollers when tensile force was applied, and a properly sloped and dimensioned
insertion pit to adequately support the pipe at the location of the most insertion stress,
namely the vertical bend down into the alignment. The most critical aspect of the
installation is the first thousand feet or so, when the insertion process is just starting
and the most drag will be present on the string as it is being installed.
39Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE
The alignment was flushed with 1,360 m3 (360,000 gallons) of water on August 31
and Sept. 1, 2009 to ensure that all the air was removed from the alignment prior to
pressure testing. The alignment passed pressure test on Sept. 1, 2009, holding
required pressure for 4 hours with no loss, at which time it was accepted as a
complete crossing.
CONCLUSIONS
Horizontal directional drilling played a major role in allowing construction of a raw
water delivery system project for the Standing Rock Sioux Tribe in South and North
Dakota. A record setting 1,463 m (4,800 LF) bore under Oahe Lake of 600 mm (24-
inch) Fusible C-905 pipe has defined an early success on the project. The crossing
presented a number of unique challenges for King Contracting, Inc., the driller that
installed the crossing, including the remoteness of the drilling site, water level issues
in the lake, adjustments to the overall layout of the drill and fusion, varying ground
conditions, and wireline system challenges.
After the drill and fusion of the pipe were completed, 1,463 m (4,800 LF) of pipe was
installed for this record setting bore. With 90 of 100 km (56 of 62 miles) of the new
transmission pipeline yet to be installed, arguably the most challenging portion of the
10 year pipeline construction process has already been installed and tested.
REFERENCES
Bueno, Sharon M. (2009). “Water Project in South Dakota” Trenchless
Technologies, September, 2009, Benjamin Media.
Bartlett and West (2009). “Standing Rock Sioux Tribe Standing Rock Rural Water
System Raw Water Pipeline Phase1 Contract 3-3”, August 2008.
40Pipelines 2010: Climbing New Peaks to Infrastructure Reliability—Renew, Rehab, and Reinvest
© 2010 ASCE