常用成語中容易讀錯的字
安步當車
安分手己
白頭偕老
百廢俱興
to achieve high quality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thorough check, calculate construction materials and technology to give the low-down the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrument unit, with the active cooperation, so as to avoid the instrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioning, shall report the test application by party representatives, representatives of the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advance written notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer of professional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineering processes must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ensure
百戰不殆
百折不撓
暴虎馮河
暴殄天物
卑躬屈膝
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha2
奔走呼號
笨口拙舌
比肩繼踵
閉目塞聽
并行不悖
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o3
病入膏肓
博聞強識
不寒而慄
不脛而走
不咎既往
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha4
不可理喻
不省人事
不著邊際
殘羹剩飯
殘垣斷壁
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o5
滄海一粟
藏污納垢
草菅人命
插科打渾
車載斗量
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha6
乘人之危
懲錢毖後
嗤之以鼻
魑魅魍魎
重道覆轍
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o7
崇洋媚外
窗明几淨
垂頭喪氣
垂涎欲滴
猝不及防
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha8
打躬作揖
大腹便便
大興土木
簞食壺漿
丟三落四
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o9
東鱗西爪
動人心弦
獨闢蹊徑
度德量利
耳濡目染
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha10
發號施令
發聾振聵
發人深省
返璞歸真
方興未艾
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o11
防微杜漸
風馳電掣
扶危濟困
負隅頑抗
改弦易轍
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha12
隔三差五
功虧一簣
觥籌交錯
狗尾續貂
呱呱墬地
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o13
管中虧豹
海市蜃樓
駭人聽聞
汗流浹背
厚古博今
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha14
呼天搶地
怙惡不悛
誨人不倦
火中取栗
掎角之勢
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o15
家給人足
家喻戶曉
狡兔三窟
矯揉造作
揭竿而起
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha16
嗟來之食
金蟬脫殼
謹小慎微
驚世駭俗
居安思危
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o17
居高臨下
鞠躬盡瘁
開門揖盜
扣人心弦
膾炙人口
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha18
潰不成軍
狼奔豕突
老牛舐犢
樂善好施
離群索居
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o19
里應外合
厲兵秣馬
良莠不齊
量體裁衣
龍潭虎穴
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha20
屢見不鮮
滿載而歸
毛遂自薦
每況愈下
蒙頭轉向
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o21
民脂民膏
冥思苦想
摩肩接踵
目瞪口呆
南轅北轍
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha22
寧缺毋濫
寧死不屈
弄巧成拙
奴顏婢膝
排懮解難
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o23
蓬頭垢面
皮開肉綻
否極泰來
樸朔迷離
潛移默化
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha24
強詞奪理
沁人心脾
情不自禁
曲高和寡
人微言輕
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o25
忍俊不禁
目不暇給
如初一轍
如法炮製
如火如荼
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha26
喪心病狂
色厲內荏
少安毋躁
少不更事
設身處地
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o27
深惡痛絕
審時度勢
韜光養晦
天旋地轉
恬不知恥
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha28
鐵杵成針
同仇敵愾
兔死狗烹
唾手可得
外強中乾
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o29
剜肉醫瘡
萬馬齊暗
妄自菲薄
望洋興嘆
危言聳聽
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha30
微不足道
惟妙惟肖
為虎作倀
未雨綢繆
味同嚼蠟
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o31
聞風喪膽
穩操勝券
無微不至
蝦兵蟹將
瑕不掩瑜
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha32
下車依始
相濡以沫
相行見絀
心廣體胖
心灰意懶
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o33
心急火燎
心曠神怡
欣悅誠服
興風作浪
尋根究底
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha34
偃苗助長
養尊處優
么五喝六
咬文嚼字
一唱一和
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o35
一蹴而就
一帆風順
一丘之貉
一語破的
油煎火燎
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha36
游刃有餘
有的放矢
有朝一日
餘勇可賈
愈演愈烈
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o37
怨聲載道
越俎代庖
載歌在舞
瞻前顧後
真知灼見
quality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, ha38
振聾發聵
質疑問難
眾矢之的
諸如此類
裝模作樣
of prod. 5.1.1.4 strictly professional transfer of process quality inspection system, handling written delivery list. The transfer r and QC personnel, make conclusions on construction quality in the future, quality form a basis of the project when completengineehe workers, technicians and construction quality inspection requests, advance written notice to the management company site eists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection system, each process was finished, filled in by tpecialning, shall report the test application by party representatives, representatives of the management company and the factory swork and, if necessary, corresponding with the related technical or construction plan key single equipment prior to commissioent unit, with the active cooperation, so as to avoid the instrument device is not properly installed and redown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-nology to give the lowd techconstruction, instrument technician prior to construction workers, have a thorough check, calculate construction materials antruction alternatives 5.1 5.1.1 the instrument construction methods General requirements 5.1.1.1 to ensure smooth instrument to achieve high quality project. 5. instrument installation consensurers check and a written record. 5.1.1.5 strictly abide by the national regulation and construction site safety regulations to ngineeut the next working procedure operation; important instrumentation engineering processes must inform the management company efessional process, must be fully installed quality inspection processes installed on disqualification, shall not be carried o39
捉襟見肘
自怨自艾
縱虎歸山
e writsystem, each process was finished, filled in by the workers, technicians and construction quality inspection requests, advancof the management company and the factory specialists is confirmed, in order to perform. 5.1.1.3 strictly quality inspection tives tion plan key single equipment prior to commissioning, shall report the test application by party representatives, representanstrument device is not properly installed and rework and, if necessary, corresponding with the related technical or construcent unit, with the active cooperation, so as to avoid the idown the construction workers. 5.1.1.2 closely linked to pipeline construction of the instrum-check, calculate construction materials and technology to give the low roughequirements 5.1.1.1 to ensure smooth instrument construction, instrument technician prior to construction workers, have a thoquality project. 5. instrument installation construction alternatives 5.1 5.1.1 the instrument construction methods General r to achieve hightion and construction site safety regulations to ensurecesses must inform the management company engineers check and a written record. 5.1.1.5 strictly abide by the national regulang proalled on disqualification, shall not be carried out the next working procedure operation; important instrumentation engineerindling written delivery list. The transfer of professional process, must be fully installed quality inspection processes instem, haquality form a basis of the project when completed. 5.1.1.4 strictly professional transfer of process quality inspection systten notice to the management company site engineer and QC personnel, make conclusions on construction quality in the future, 40