Possible Formulas Used on Project Management Professional Certification Exam
Collected by Kristi L. Myers, Rhonda Brittain, Dale Kelly
Refined and compiled by Jeanne Henderson and Kevin Burns
Updated for PMBOK 2000 by Jeff Harma (changes shown in bold)
Time
P= pessimistic
O=optimistic
Activity Duration (t) = optimistic + 4 (most likely) + pessimistic (This is also referred to as the Pert Mean)
6
Activity Duration = Work Quantity / Productivity Rate
Standard Deviation (s) = pessimistic-optimistic (This is also referred to as the Pert Standard Deviation)
6
Total Duration (T) = task duration 1, + task duration 2, + task duration 3, +……………task duration n
Pert Variance = [O-P / 6]2
Float = Late float – Early Float
Communication
Number of Communication Paths (or Communication Channels) = Number of people x (Number of people – 1)
2
Risk
Statistical Independence: Sum of the Probabilities = 1
When using a decision tree, multiply the percentages on the appropriate branches together to get your probability of that series of events happening.
Quality
Mode = Most frequent value
UCL = Upper control limits
LCL = Lower control limits
The Variance is the mean of the squares of the deviations of the observations from their mean.
The Standard Deviation is the positive square root of the variance.
Example: 17, 17, 19, 22 The mode would be 17.
Bi-modal: Example: 17, 17, 17, 19, 19, 22 The answer: 17, and 19.
Median = Middle value, when all values are in ascending or descending order. If there is an even number of values, take middle two values and divide by 2.
_
Mean (x) = Sum of all values / number of values
Capacity Index = (UCL – LCL)
6(
Standard Deviation (() =
Standard Deviation from multiple sources = (
Standard Deviation of sample ( ( ) = (
( n
Variance (var) = (2
Example: Find the variance and standard deviation of the 5 observations
6, 7, 5, 3, 4
(a) First compute the mean.
x = 6 + 7 + 5 + 3 + 4 = 25 = 5
5 5
(b) The deviation of any observation x from the mean is the difference x - x , which may be either positive or negative. Use this arrangement to compute the variance:
Observation
Deviation
Squared deviation
x
x - x
(x - x )2
6
6 – 5 = 1
(1)2 = 1
7
7 – 5 = 2
(2)2 = 4
5
5 – 5 = 0
(0)2 = 0
3
3 – 5 = -2
(-2)2 = 4
4
4 – 5 = -1
(-1)2 = 1
Sum = 0
Sum = 10
The sum of the squares of the deviations from the mean is 10., The variance is therefore
Variance = sum of squared deviations = 10 = 2
Number of observations 5
(c) The standard deviation is the square root of the variance.
· 2 = 1.4
Rule of 7
This means the process is out of control if one of the following is occurring.
· Seven points in a row will be on one side of mean =(1/2)7 = 1/128 = .0078
· Seven points in a row will be on one side or other of mean = (1/2)7 + (1/2)7 = 1/64 = .0156
Cost
Cost - Earned Value Analysis
Acronyms
CV = Cost Variance
PV = BCWS = Budgeted Cost of Work Scheduled = Planned Value
EV = BCWP = Budgeted Cost of Work Performed = Earned Value
AC = ACWP = Actual Cost of Work Performed = Actual Cost
SPI = Schedule Performance Index
CPI = Cost Performance Index
SV = Schedule Variance
VAC = Variance at Completion
BAC = Budget at Completion
EAC = Estimate at Completion
ETC = Estimate to Complete
Formulas
Cost Variance CV ($) = BCWP – ACWP = EV - AC
Cost Variance CV(%) = BCWP – ACWP x 100 = EV - AC x 100
BCWP
EV
Total Cost Variance = (Planned Cost per Unit – Actual Cost per Unit) x Actual Units
% Complete = BCWP x 100 = EV x 100
BAC
BAC
% Spent = ACWP x 100 = AC x 100
BAC
BAC
Cost Performance Index (CPI) = BCWP / ACWP = EV / AC (< 1 = over budget, > 1 = under budget)
Schedule Performance Index (SPI) = BCWP / BCWS = EV / PV (<1 = behind schedule, >1 = ahead of schedule)
Schedule Variance SV($) = BCWP – BCWS = EV - PV
Schedule Variance SV (%) = SV($) / BCWS = SV($) / PV
Variance at Completion (VAC) = BAC – EAC
Estimate to Complete (ETC) = EAC – ACWP = EAC - AC
Estimate at Completion (EAC) = ACWP + (BAC – BCWP) = AC + (BAC - EV)
Independent Forecast = ACWP + BAC – BCWP = AC + BAC - EV
CPI
CPI
And look at EAC from the CPI View and the SPI View
EAC = (ACWP / BCWP) * BAC = BAC / CPI = (AC / EV)*BAC = BAC / CPI
EAC = (BCWS / BCWP) * BAC = BAC / SPI = (PV / EV)*BAC = BAC / SPI
Cost Value of Money
PVIF = Present Value Interest Factors
FV = Future Value
i = interest
NPV = Net Present Value
PV = Present Value
__________________________________________________________________________________________
Payback period = Investment / After-tax cash flow (Expressed in $ per period)
Defined as the length of time required to recover the first cost of an investment from a net cash flow produced by that investment for an interest rate of zero.
Example:
Evaluation of Projects V and W
Project
Investment, $
1
2
3
4
5
6
Payback Period Years
NPV at 10%
IRR
V
2000
1000
1000
2
467
23.4%
W
2000
800
800
800
800
800
800
2.5
1464
32.7%
PBP for V = $2000 / $1000 per month = 2 months.
Accounting Rate of Return = Annual After-tax Net Income / Investment
___________________________________________________
Net Present Value (NPV) = FV / (1 + i)n
or
Net Present Value (NPV) = PV of Revenue – PV of Cost
_____________________________________________________________________________
NPV annually (PV) = FV / [(1 + i)n + (1 + Iin-1 + (1 + i)n-2……………+ ((1 + I)1]
Present Value (PV) = FV / (1 + r) n Where r = interest rate, n = periods
Present Value (PV) = FV * PVIF
Future Value (FV) = PV * (1 + r)n Where r = interest rate, n = periods
Future Value (FV) = PV / PVIF
Future Value Annually (FV) = PV x [(1 + i)n + (1 + Iin-1 + (1 + i)n-2……………+ ((1 + I)1]
Benefit Cost Ratio (BCR) = PV of Revenue / PV of Cost
Expected Monetary Value (EMV) = Outcome x Probability of Outcome
Cost - Depreciation
Straight line depreciation = (Investment - Salvage) / Number of years
Sum of Years Digits (SYD) = (Investment - Salvage) x (Number of Years Remaining / Sum of Years)
Double Declining Balance ((DDB) = (Investment or Remainder) x (2 x Straight line %)
Cost – Other
Fixed Price plus Incentive Fee = Actual Cost + Fixed Fee + Incentive
Where Incentive = Over/Underage x Seller’s %
For example: A pre-Arranged 30% of $100K overage costs the seller (negative) $30K
Another example: 20% of $50K underage nets the seller (positive) an extra $10K
IRR = Internal Rate of Return – The discount rate that equates the present value of cash inflows with the initial investment associated with a project, thereby making NPV = 0. The criterion when the IRR is used to make accept-reject decisions is as follows: If the IRR is greater than the cost of capital, accept the project; if the IRR is less than the cost of capital, reject the project. This criterion guarantees that the firm earns at least its required return. Such an outcome should enhance the market value of the fir and therefore the wealth of its owners.
The IRR can be found either by using trial-and-error techniques or with the aid of a sophisticated financial calculator or computer.
Formula for finding IRR for an Annuity:
1. Calculate the payback period for the project.
2. Use a table (the present-value interest factors for a $1 annuity, PVIFA) to find, for the life of the project, the factor closest to the payback value. The discount rate associated with that factor is the internal rate of return (IRR) to the nearest 1 percent.
Estimating
Order of Magnitude (-25% to +75%) gross
Conceptual
Preliminary
Definitive (-5% to +10%) most precise
Control / Budget / Design / Appropriation (-10 to +25% (other)
= ( var
((x - x)2
n
(
((1)2 + ((2)2 + ((2)2 …….+((n)2